CASE STUDY
NATIONAL ENERGY INFRASTRUCTURE PROJECT
Delivering specialist enabling, ecological and land-based services across a nationally significant energy infrastructure scheme.
35km
Cable Route
1,575,000m2
Land Reinstated
60km
Easement Fenced
0
Lost Time Injurys
Project Overview
MRF Contracting was instructed by a Tier 1 contractor to deliver the full vegetation clearance, fencing and land remediation packages in support of the Richborough Connection Project.
The works involved enabling activities across multiple locations, including specialist fencing installations, large-scale de-vegetation operations and the reinstatement of agricultural land following construction. By utilising our in-house teams and specialist plant fleet, MRF provided an integrated solution that supported programme delivery whilst ensuring environmental compliance and effective stakeholder management.
Client
Confidential Tier 1 Contractor
Sector
Energy Infrastructure
Location
South East
Services
Enabling & Environmental
Duration
8 Months
Key Services Delivered
- Vegetation Clearance
- Ecological Mitigation
- Specialist Fencing
- Land Reinstatement
- Agricultural Liaison
The Challange
- Large linear infrastructure corridor
- Multiple landowners and stakeholders
- Ecological and environmental constraints
- Agricultural land protection requirements
- Challenging access and ground conditions
- Programme-critical works alongside main contractor activities
- Full land reinstatement following construction
Vegitation management
Fencing
Land Reinstatement